
CIVIL CONSTRUCTION
Shepparton Corridor Upgrade Project
Project Start/Finish Date: August 2021 to February 2022
Client: Coleman Rail
Murchison East Loop
Earthworks – Strip Topsoil and Organic material, Bulk Earthworks and Subgrade Preparation, Track Formation Works.
Drainage - Construct and installation of new formation and access track cess drains. Drainage was installed across the Murchison Passing Loop.
Stabling Yard, Mainline Slew and Turn out
Earthworks - Strip Topsoil, Bulk Earthworks – Cut to Fill and load out of excess material, Lime stabilization, Place and compact – Structural Fill, Capping Bottom Ballast.
Drainage - RCP Pipe, Cess Drainage, Cross Track Culverts, Subsoil Drainage, Intertrack Drainage.
Piling -Bored Piling works (including placement of Pile cage & rag bolt sets, Services Gantry Piles, Light pole and CCTV piles, Amenities Building Slab and footings, Storage Building slab and footings.
Construction of Karibok Park - Retardation Basin and Recreational Area
Project Start/Finish Date: August 2021 to January 2022
Client: Greater Shepparton City Council
-
Earthworks & Basin Construction
-
Drainage
-
Rockworks
-
Fencing
-
Reinstatement Works
Murray Valley Highway/Lady Augusta Road – Intersection Upgrade Works
Project Start/Finish Date: August 2021 to October 2021
Client: VicRoads
-
Earthworks – Excavation of approx. 601m3 of existing material, place and compact Type B fill, regrade of existing shoulders.
-
Drainage Works – Install 43Lm of 450dia RRJ drainage, 12Lm Box Culverts, SD1981 Wingwalls and SD1991 and SD1992 Endwalls.
-
Pavement Construction – Placed 173T of 100mm Class 1 size 20 crushed rock to shoulders, base course, 933T of 200mm Class 1 size 20 crushed rock, subbase, 1073T of 230mm Class 3 size 20 crushed rock, and 148m3 80mm Type A fill layer.
-
Spray Bituminous Surfacing works - Placed over 7660m2 of 10/7mm emulsion primerseal and 14/7mm XSS final seal, Line marking, RRPM’s and reinstall/install guideposts, installation of new signs, Flexible W-beam and GREAT terminals.
Salvation Army Carpark
Project Start/Finish Date: May 2021 to September 2021
Client: GMR Engineering Services
Construction of Car Parks – Kerb & Channel and Drainage works
Earthworks, Demolition & Preparation, Car Park Lighting, Stormwater Drainage, Pavement & Surfacing, Concrete Kerb & Paving, Traffic Management, Site Reinstatement