top of page

LANDFILL & WASTE MANAGEMENT

Cosgrove 2 Cell 4

Project Start/Finish Date: October 2021 - March 2023

Client: Greater Shepparton City Council

Removal of existing infrastructure, Establishment of electrical mains, Construction of drainage and stormwater holding dam, Construct permanent Landfill Cell Composite Capping.

Cosgrove 3 Cell 2

Project Start/Finish Date: August 2021 - May 2022

Client: Greater Shepparton City Council

Subgrade preparation works, construct permanent landfill liner system, Construct Leachate collection system including cell risers.

Eaglehawk Landfill Rehabilitation Works

Project Start/Finish Date: May 2021 - May 2022​

Client: Greater Bendigo City Council

Stage 1A – Hardstand Area, Access Road, Gabion Retaining Wall –

Bulk earthworks including on site and off site haulage to site, Soil testing, Supply, place and compact select fill to hard stand area, Supply, place and compact crushed concrete road pavement to the hard stand area and access road, Supply all materials and construct a gabion wall, Supply and construct temporary storm water pipe culverts.

Stage 1 – Capping Parts of Cells-

Bulk earthworks including on site and off site haulage to site, Supply, place and compact:

• Select fill, • Clay Fill and • Mulch/topsoil,

Soil testing, Supply, place and compact select fill, Supply, place and compact crushed concrete to access road areas, Construct stormwater contour bunds, catch drains and culverts.

Western Water RWP Storage Liner, Mount Cottrell

Project Start/Finish Date: February - March 2020​

Client: Western Water

Works included  to replace and extend the Biosolids Storage Area (BSA) liner and surface:

  • Earthworks associated with removal and relocation of contaminated clay/sludge material from existing BSA

  • Removal of all vegetation from within the BSA including within the existing stormwater drains

  • Excavation, grading proof rolling and all other activities associated with surface preparation of the BSA lay liner

  • Construction of CTCR liner and surface drain with all earthworks

  • Installation of DN300 RC class 4 culverts

  • Testing and Commissioning

  • Works survey set out

  • Traffic Management

Cosgrove 3 Cell 1, Leachate Ponds and Cosgrove Clay Pit Rehabilitation

Project Start/Finish Date: April 2018 - July 2019

Client: Greater Shepparton City Council

  • Construction new landfill cell including installation of over 100,000m2 of geosynthetic landfill liner

  • Removal of 45,000m3 of material for new cell and leachate ponds

  • Construction of 24,800 m2 leachate pond geosynthetic liner

  • Installation of new leachate collection system including 5,500t of aggregate

  • Rehabilitation of the Cosgrove Clay Borrow Pits through the placement of 27,700m3 of site won material

 

Cosgrove 3 Landfill Site Development Time-Lapse Video​

Cosgrove 2

Location: Shepparton / Cosgrove

Client: Greater Shepparton City Council

 

  • Construction of Cosgrove 2 Cell 4 side liner lift 4 

  • Construction of 750m3 Clay liner under level 1 Supervision in active cell.

Benalla Landfill Cell Two Construction

Location: Benalla, Victoria

Client: Benalla Rural City Council

Bulk out cell two construction including:

 

  • Clearing and grubbing 29,500m2, Excavation  

  • Cut 218,400m3, Construction of access track, stormwater diversion bund, and culverts.

  • Install Jute mesh on batters, hydro-mulch and sediment traps.

Violet Town Landfill Rehabilitation Construction Works

Project Start/Finish Date: December 2022 - November 2023

Client: Strathbogie Shire Council

Construction of landfill Cap including Gas Extraction system, Clay liner, subsoil fill, Topsoil, Seeding, access road and drainage, dam construction. ~ 60,000m3 of Material trucked into site.

Castlemaine Landfill Construction

Project Start/Finish Date: August 2022 - May 2023

Client: Mt Alexander Shire Council

Construction of Landfill Cap, Cells 4, 5, 7A, 7B and remainder of Cells 1, 2 & 3. Construction of a compacted clay sideliner extension, Construction landfill gas extraction system with geosynthetic strip drains, Installation of GCL and LLDPE and stormwater drains.

bottom of page