PROJECTS
Originally established as Pearse Earthmoving, Apex Earthworks has been providing earthmoving, construction and excavation services in the Goulburn Valley region for over 40 years. In that time, we have successfully completed hundreds of projects from small land clearing, to major construction works and have become an industry leader. We have worked extensively with State and Local Government departments, public infrastructure owners and operators, developers and other private clients.
The Apex Earthworks team has the knowledge and experience to deliver projects and offers safety excellence, project delivery certainty, efficiency and value-for-money.
To find our more about our RAIL capabilities, head to APEX RAIL.
Western Water RWP Storage Liner, Mount Cottrell
Cosgrove 3 Cell 1, Leachate Ponds and
Cosgrove Clay Pit Rehabilitation
Project Start/Finish Date: April 2018 - July 2019
Client: Greater Shepparton City Council
-
Construction new landfill cell including installation of over 100,000m2 of geosynthetic landfill liner
-
45,000m3 of bulk earthworks for new cell and leachate ponds
-
Construction of 24,800 m2 leachate pond geosynthetic liner
-
Installation of new leachate collection system including 5,500t of aggregate
-
Rehabilitation of the Cosgrove Clay Borrow Pits through the placement of 27,700m3 of site won material
Numurkah Solar Farm
Project Start/Finish Date: October 2018 - March 2019
Client: Downer
-
95,000m2 of subgrade improvements through lime stabilisation
-
Bulk earthworks for substation hardstand
-
95,000m2 of internal and CFA access road construction
-
Installation of box culverts including headwalls and beaching
-
Wet hire plant for dust suppression and other minor works
Goulburn Murray Water Connections Project-
MV20 Pipeline Construction & On Farm Works
Project Start/Finish Date: April – August 2019
Client: John Holland
-
Installation of 910m of PN4/PN8 DN450/800mm gravity pipeline
-
Installation of 4 new closed conduit meter outlets
-
Supply & Installation of new Stock and Domestic (D&S) Outlets and off take structures
-
Supply, installation & construction of Simkin On Farm Works Package
-
Installation of new 36m DN600 PN8 Subway structure including cut off walls
-
Decommissioning of existing GMW channel
-
Decommission and removal of existing channel infrastructure (off take structure, headwall, subway, Dethridge meters & outlet structures)
-
Site reinstatement including rehabilitation of farm assets, tree pruning and removal
Goulburn Murray Water Connections Project
CG41 RP03 Pipeline
Project Start/Finish Date: May – August 2019
Client: John Holland
-
Installation of 1779m of PN4/PN8 DN400/800mm CG26/28/9 gravity pipeline
-
Installation of 897m of PN4 DN400/310mm CG23/28/9 gravity pipeline
-
Installation of 10 new Closed Conduit Meter Outlets on principal pipelines
-
Supply and Installation of 6 new Stock and Domestic (D&S) Outlets on principal pipeline
-
Installation of 1 new Meter Outlet on retained channel
-
GMW Channel & Structures Decommissioning
-
Supply and installation of 2 Type B off take structure
-
Construction of Souter On Farm Works (OFW) package
-
Site reinstatement including rehabilitation of farm assets, tree pruning and removal
Latham Road Upgrade
Location: Echuca, Victoria
Client: Shire of Campaspe
Construction of 2.119 kilometres of Latham Road east from Braund Road including:
-
Earthworks and construction of crushed rock pavement with a 6.4m wide pavement, 6.2m wide two coat seal, linemarking and signage
-
Construction of cross road drainage culverts and wayside table drains
-
Cement stabilisation of pavement sub-base through floodway
-
Installation of entrance culverts at all existing driveways
-
Traffic Management to enable road to remain open at all times during the works
Biomx Civil Works – Stage 1 & 2
Location: Stanhope, Victoria
Date: Feb 2018- June 2019
Client: Biomix
Construction of civil works for new green waste recieval facility and composting hardstands, including:
-
30,000m3 of structural fill excavation, conditioning, and placement
-
35,00m2 of cement treated hardstand construction
-
12,000m2 of roads and
-
7,500m2 of concrete pavement.
-
Interface and co-ordination works so as to not impact on existing operations
-
Works completed 1 month ahead of schedule
St Mary's Carpark, Seymour
Location: Seymour, Victoria
Client: St Mary's College
Construction of new school entry and staff/ visitor carpark outside new administration building including:
-
New entry onto High St
-
Construction of 2440m2 asphalt carpark - Primer and 40mm Hotmix
-
Construction of storm water drainage system, side entry pits and installation of oil water separator,
-
Kerb and Channel
-
Footpaths
Channel Remediation - Murray Valley 4/1 and 1/4/1
Location: Cobram, Victoria
Client: John Holland / GMW
-
Remediation of 2.06km of existing channel
-
Rehabilitation of clay liner
-
55,000m3 bulk earthworks
-
Rock armour placement
-
Installation of 4 outlet and 2 regulator structures
-
Fencing
Channel Remediation - TN616-618
Location: Tongala, Victoria
Client: GMW / TransCom Connect
-
Remediation of 1.7km of channel
-
HDPE and GCL re-lining
-
Coordination and consultation with 5 private landowners
-
35,000m3 bulk earthworks
-
Site access and cultural heritage constraints
-
Successful delivery of project throughout the regions wettest winter in over 35 years
Strathmerton WMF Lagoon 3 Rehabilitation
Location: Strathmerton, Victoria
Client: Goulburn Valley Water
Installed a 600 mm thick compacted clay liner over the floor of the Winter Storage (Lagoon 3) including importing material geo-fabric and rock armour
Cosgrove 2
Location: Shepparton / Cosgrove
Client: Greater Shepparton City Council
-
Construction of Cosgrove 2 Cell 4 side liner lift 4
-
Construction of 750m3 Clay liner under level 1 Supervision in active cell.
BP Service Station, Jeriderie
Project Start/Finish Date: November 2019
Client: Becon Constructions (Aust) Pty Ltd
Civil works for large service station including large truck facilities:
-
Excavation to subgrade level across site
-
Install crush rock base of concrete works
Western Water RWP Storage Liner, Mount Cottrell
Project Start/Finish Date: February - March 2020
Client: Western Water
Works included to replace and extend the Biosolids Storage Area (BSA) liner and surface:
-
Earthworks associated with removal and relocation of contaminated clay/sludge material from existing BSA
-
Removal of all vegetation from within the BSA including within the existing stormwater drains
-
Excavation, grading proof rolling and all other activities associated with surface preparation of the BSA lay liner
-
Construction of CTCR liner and surface drain with all earthworks
-
Installation of DN300 RC class 4 culverts
-
Testing and Commissioning
-
Works survey set out
-
Traffic Management
Yakka Basin Construction
Project Start/Finish Date: March - August 2020
Client: Greater Shepparton City Council
45,000m3 of bulk earthworks, deep RCP and Pit Drainage runs, Bio-retention swale drain and rockworks, supply and install new pumping station and DN150 rising main, filtration system, clay liner construction, top soiling, landscaping and hydroseeding, fencing installation.