top of page

WATER INFRASTRUCTURE

Water Efficiency Project - WEPCSP-064 - RO10 RO01 RO 11 Pipeline

Project Start/Finish Date: May 2023 to September 2023

Client: Goulburn Murray Water

Installation of 7kms of GMW pipeline and associated meter treatments, channel decommissioning, including a total of 13 road crossings and a rail crossing. 7km of pipe was installed within 2 months.

Water Efficiency Project - WEPCSP-026 - MV35 RP04 MV 13/6 Pipeline

Project Start/Finish Date: May 2022 to November 2022

Client: Goulburn Murray Water

Installation of 7kms of GMW pipeline and associated meter treatments, channel decommissioning road crossing installations.

Lake Eppalock Rock Wall Excavation Works

Project Start/Finish Date: July 2021 to October 2021​

Client: Goulburn Murray Water

Excavation and stockpiling of approximately 13,000 bank m3 of basaltic rock and palagonite tuff from behind the primary spillway walls while mitigating damage to the primary spillway reinforced concrete walls

Goulburn Murray Water Connections Project- RO21RP03 Pipeline Construction & On Farm Works

Project Start/Finish Date: ​March to October 2020

Client: John Holland

  • Decommissioning of existing GMW Channels and Structures

  • Installation of new GMW HDPE Pipelines

  • Installation of Meter Outlets

  • Installation of Pipeline Features (inspection of pits, air valves and outlets)

  • Construct Type B Offtake Structures

  • Relocate existing GMW HDPE Channels

  • Supply and Installation of 2 new stock and domestic Meter Outlets 

  • Installation of level sensor, solar pumps, water tanks and D&S lines

  • On Farm Works - site reinstatement including rehabilitation of farm assets,  installation of new fencing, tree pruning

  • Hydrostatic Testing

CG09RP01B - Principal Gravity Pipeline & OFW Package

Project Start/Finish Date: November 2019 - June 2020​

Client: John Holland

Construction of 2.7km of HDPE gravity pipeline predominately 1200mm dia reducing down to 800mm. Including installation of

  • offtake structures, 4 meters, 2 S&D,

  • 1000mm dia under bore road crossings,

  • connections,

  • decommission of 3.7km of channels and associated infrastructure.

Goulburn Murray Water Connections Project- MV20 Pipeline Construction & On-Farm Works

Project Start/Finish Date: April – August 2019​

Client: John Holland

  • Installation of 910m of PN4/PN8 DN450/800mm gravity pipeline

  • Installation of 4 new closed conduit meter outlets

  • Supply & Installation of new Stock and Domestic (D&S) Outlets and off take structures

  • Supply, installation & construction of Simkin On Farm Works Package

  • Installation of new 36m DN600 PN8 Subway structure including cut off walls

  • Decommissioning of existing GMW channel

  • Decommission and removal of existing channel infrastructure (off take structure, headwall, subway, Dethridge meters & outlet structures)

  • Site reinstatement including rehabilitation of farm assets, tree pruning and removal

Goulburn Murray Water Connections Project CG41 RP03 Pipeline

Project Start/Finish Date: May – August 2019

Client: John Holland

  • Installation of 1779m of PN4/PN8 DN400/800mm CG26/28/9 gravity pipeline

  • Installation of 897m of PN4 DN400/310mm CG23/28/9 gravity pipeline

  • Installation of 10 new Closed Conduit Meter Outlets on principal pipelines

  • Supply and Installation of 6 new Stock and Domestic (D&S) Outlets on principal pipeline

  • Installation of 1 new Meter Outlet on retained channel

  • GMW Channel & Structures Decommissioning

  • Supply and installation of 2 Type B off take structure

  • Construction of Souter On Farm Works (OFW) package

  • Site reinstatement including rehabilitation of farm assets, tree pruning and removal

Channel Remediation - Murray Valley 4/1 and 1/4/1

Location: Cobram, Victoria

Client: John Holland / GMW

  • Remediation of 2.06km of existing channel 

  • Rehabilitation of clay liner 

  • 55,000m3 bulk earthworks 

  • Rock armour placement 

  • Installation of 4 outlet and 2 regulator structures 

  • Fencing

Channel Remediation - TN616-618

Location: Tongala, Victoria

Client: GMW / TransCom Connect

  • Remediation of 1.7km of channel 

  • HDPE and GCL re-lining 

  • Coordination and consultation with 5 private landowners 

  • Site access and cultural heritage constraints 

  • Successful delivery of project throughout the regions wettest winter in over 35 years

Strathmerton WMF Lagoon 3 Rehabilitation

Location: Strathmerton, Victoria

Client: Goulburn Valley Water

Installed a 600 mm thick compacted clay liner over the floor of the Winter Storage (Lagoon 3) including importing material geo-fabric and rock armour

GOULBURN RIVER BANK STABILISATION - TOM COLLINS DRIVE, SHEPPARTON

Project Start/Finish Date: February 2024 - March 2024

Client: Greater Shepparton City Council

Rectification and Installations to stabilise and re-establish the river bank alongside Tom Collins Drive damaged after the 2022 floods.

Surface and bank preparation including removal of vegetation, topsoil stripping and removal of unsuitable material. 

Installation of Geo Fabric, over 1300 tonnes of Rock sourced from local quarries and Rip Rap for erosion protection.

Reinstatement and topsoiling of disturbed areas and timber bollards.

Greater Shepparton City Council Project Link

bottom of page